Founded over 140 years ago in the Victorian gold fields, Orica is one of the world’s largest explosives provider specialising in blasting systems, mining chemicals and geotechnical monitoring for mine sites around the world.
The Problem
Orica had successfully demonstrated the technology and business case with around 6 prototype units deployed in the field. However, each of the units was taking over 1 month to build and required the original design team to complete the assembly. This meant the Fragtrack project was carrying a high amount of key person risk with its design team and were unable to continue developing new solutions.
The Technical Solution
Our team of manufacturing technicians in conjunction with our design team helped Fragtrack to achieve:
Less than 1 month to setup manufacturing and eliminate key person risk
Significant reduction in manufacturing time as compared to customer’s internal team
12 month warranty for units deployed in harsh mining conditions worldwide
The Outcome
Orica has been able successfully commercialise FRAGTrack and over 100 units have been manufactured and deployed globally. Learn more about FRAGTrack contact Orica Australia